Home About Us Products Services Careers Contact Us
 
iNetFrame adopts a proven implementation methodology that incorporates the best practices in web-based solution implementation. The built-to-adapt iNetFrame solution and the proven methodology ensure the success of your implementation, within a matter of days.

You work jointly with iNetFrame's Professional Services to reduce implementation costs. The table below summarizes the key tasks/milestones and the owner for each task.
 

#

Task/Milestone

Owner

Comments

1

PO released

Customer

2

Kick-off meeting

iNetFrame

Introduction meeting that identifies the team members involved. The customer will be provided instructions on how to access the out-of-the-box solution, hosted by iNetFrame

3

Assessment

Customer

iNetFrame will guide you through the process. If the customer desires so, iNetFrame can take ownership for this. Results in a requirements definition document

4

Requirements Definition

Customer

iNetFrame can take ownership for this, if desired by the customer

5

Statement of Work

iNetFrame

iNetFrame prepares this based on the Requirements Definition document

6

Finalized agreement

Customer

This is the basis on which implementation project begins

7

Begin implementation

iNetFrame

Customer will have access to a test server during implementation

8

End implementation

iNetFrame

9

Acceptance testing

Customer

At this stage, it is the implementation team that is involved in the testing

10

Installation and setup

iNetFrame

This is the installation and setup of the customized project at the customer premises

11

User acceptance testing

Customer

At this stage, end users can take part in the testing

12

Training

iNetFrame

Includes administrator and end user training. Can be conducted at different times at additional cost

13

Deployment

Customer

Live deployment

14

Follow up

iNetFrame

iNetFrame technical